NOVEMBER 2018

The building is standing taller and is transforming the city skyline everyday through the construction progress.  Structural steel has been installed to the entire Level 5 and in some parts of Level 6. With the level 5 floor pour scheduled for the 2nd of November. The mezzanine office structural steel is now onsite with install due imminently with an aim of pouring this early to mid-November. The façade panels for level 1 are due for arrival and then will be followed by installation. Fit-out of services are progressing well on Level 1 and 2 with Level 3 services starting within the next week. The Hotel and Residential Units are now SOLD OUT!